Case Study: FRP Scrubber Demonstration

July 4, 2018

FRP Scrubber Demonstration


UltraAnalytix™ data was collected from sections of a retired FRP scrubber that had been used to clean vented vapours. The customer is a multinational chemical corporation, a world leader in titanium technologies, fluoroproducts and chemical solutions.

This case study demonstrates the value of the UltraAnalytix™ system for determining Remaining Service Life and as a guide for repair and replacement. It revealed that replacement of the scrubber would not have been necessary for at least another 19 years, if not more, for considerable potential cost savings.


Retired FRP scrubber had another 19 years of service life remaining.

1 of 4 scrubber sections. UltraAnalytix™ evaluation showed this retired scrubber had at least another 19 years of service life remaining.

BACKGROUND

UTComp® data was collected from sections of a retired FRP Scrubber that had been used to clean vented vapours. The scrubber used caustic liquor to remove chlorides. This is the 1st time that UTComp® Evaluation has been completed for this equipment. The vessel was insulated and insulation was removed from the areas to be inspected.

The plan for the demonstration was as follows:

  1. Customer removed the equipment from service. The scrubber was disassembled, placed on the ground and the end covered to ensure that UTComp was “blind” to any internal visual clues.
  2. Insulation was removed so that UTComp data could be collected directly on the surface of the scrubber.
  3. UTComp data was collected on 5 sections and 3 reinforcements and analysis was completed.
  4. UTComp returned to the site to witness the cutting of the scrubber sections where the UTComp data was collected.
  5. Comparisons were made.

Photo 2: Cut section with corrosion barrier damage

The photo to the left shows the cut out section of concern by the customer. As can be seen, the interior of the scrubber shows significant visual corrosion barrier damage. However, this is a surface concern only and the shell shows good condition and remaining strength. This was validated by the UTComp System, which did not require confined space entry or destructive testing or holes to be cut in the equipment.

Photo 3: Close-up of the corrosion barrier damage and the shell

To the right is a close up of the corrosion barrier damage and the shell. It can be seen that the damage to the scrubber is limited to the surface of the interior.

Using the UTComp Analysis a 1.25mm corrosion barrier damage was detected and confirmed using measurements.

CONCLUSION

UTComp completed the analysis of the files collected and the results are in the graph below.

UTComp recommended that the next inspection be completed in 2018, and estimated the year this equipment will reach its critical Percentage of Design Strength (20%) will be 2034, 19 years from the date of the inspection. Therefore, had this customer used the UTComp System to predict Remaining Service Life and as a guide for repair and replacement there would have been considerable cost savings and replacement would not have been necessary for at least another 19 years, if not more.

View as a PDF

Non-Destructive Evaluation (NDE) Methods for FRP

Comparison of NDE methods for determining Remaining Strength Factor of FRP for completion of Assessment as per proposed Part 16 update to API 579-1/ASME FFS-1:

NDE Method
Acoustic Emission (AE)
Acousto-ultrasonics (AU)
Attenuation-based ultrasonics (UAX)
UltraAnalytix (UAX+)
Applicable Standard
ASTM E1067
ASTM E1495
ASTM C1332¹
Combines ASTM C1332 & E1495
Inspector Certification Available
ISO, ASNT, SNT-TC-1A
SNT-TC-1A
SNT-TC-1A
SNT-TC-1A
Included in ISO or ASNT Training



Number of Calibration Specimens Required for an Inspection
0
1 or 2
2
0
Destructive Testing and Analysis of Calibration Specimens Required



Available Equipment Provides Output Values



Automated Processing for PDS Available



Remaining Strength Factor and Remaining Life Provided